November 8 2010 Update

110810 House1
The foundation guys removed the wall forms one by one.  This is the three car garage.  They will have to fill it with a ton of dirt.

110810 House2
They filled the tubes that will soon be the columns in the front of the house

110810 House3 110810 House4 110810 House5
Lots of wall forms

House Update November 11 2010

111110 House1
Backfilling started by Mahaffey Enterprises

111110 House2
The foundation guys painted moisture barrier on the concrete walls and tube

111110 House3
The daylight basement was insulated with styrofoam and more dirt will be filled and compacted

111110 House4
Another back hoe was brought out
111110 House8

111110 House6 111110 House7 
The foundation guys set up the water and sewer lines around the perimeter of the house

111110 House9
Filling the three car garage with dirt

111110 House5 
The moisture barrier line on the side of the house